Hyperscale Data (NYSEAMERICAN:GPUS) reported third-quarter revenue growth of 84% and a narrower net loss as executives outlined plans to convert a Michigan Bitcoin mining facility into an artificial intelligence data center and divest its Ault Capital Group businesses in 2027.
Revenue rose to approximately $45 million from just over $24 million a year earlier, Chief Financial Officer Ken Cragun said on the earnings call. The company posted a quarterly net loss of nearly $13 million, compared with nearly $14 million a year earlier.
Revenue Growth and Losses
For the first nine months of 2026, revenue increased 65% to $124 million from just over $75 million in the prior-year period. The net loss widened to more than $62 million from nearly $36 million.
Cragun attributed the revenue growth partly to the reconsolidation of defense business Gresham Worldwide at the end of 2025, after it emerged from Chapter 11. The prior-year periods did not include Gresham. Results also benefited from a litigation settlement tied to a legacy investment at Ault Lending and unrealized gains on equity investments, he said.
Cragun said higher operating expenses and noncash interest from debt discount amortization contributed to the nine-month loss. The company also expensed development work on digital asset tokenization initiatives.
Third-quarter EBITDA, a non-GAAP measure, was positive $0.3 million, compared with negative $6 million a year earlier. Cragun cautioned that the quarter benefited from noncash fair-value gains that can vary between periods. Nine-month EBITDA was negative $28 million.
Circle 8 Crane generated just over $12 million in quarterly revenue, up 26%, helped by higher service rates and better equipment utilization, Cragun said. CEO Will Horne said its fourth-quarter revenue had so far been consistent with third-quarter levels.
Michigan Data Center Conversion
Hyperscale stopped Bitcoin mining at its Michigan facility on Sept. 1 to prepare for AI hosting. Horne said the company remains on track to bring an initial 10 megawatts online in December and another 10 megawatts in March. Asked for a more precise date, he said he would expect the first phase in the later part of December.
The company has an agreement with an unnamed neocloud provider. Once the initial 20 megawatts are fully operational, Horne projected approximately $50 million in annual revenue, $20 million in net income and $28 million to $29 million in EBITDA from the contract. He said much of the power cost would be passed through to the customer.
Executives said they were honoring the customer’s request not to disclose its identity. Jay Looney, CEO of Alliance Cloud Services, the Michigan operation, said discussions about potential expansion were continuing, though the immediate focus was completing the initial deployment.
Horne said a potential expansion to 52 megawatts of critical IT capacity could become operational by the end of 2028. At that scale, he projected net income of close to $65 million and EBITDA approaching $90 million. Those figures depend on an expansion that has not yet been completed.
The customer has paid Hyperscale $20.5 million, including nonrecurring charges, a security deposit and a one-time fee recognized in the third quarter, Horne said. He estimated the current build-out would cost about $121 million and put total investment in the facility, including land and building, at nearly $150 million.
Financing and Divestiture Plans
Horne said Hyperscale is seeking $100 million in project-level financing through Newmark and hopes to refinance more expensive debt. He said the company is targeting late January or early February for a first tranche and hopes to obtain a rate closer to 8%. The financing has not been finalized.
Ault said the company sold Bitcoin to help fund development and had suspended its at-the-market equity program after hearing shareholder concerns about dilution. Horne said the program’s size had also been reduced. Bitcoin mining continues in Montana, where Horne said operations were running at a slight loss at current Bitcoin prices.
The planned Ault Capital Group divestiture is intended to leave Hyperscale more focused on data centers. Horne said the separation could result in a gain on deconsolidation and a receivable for Hyperscale reflecting its investment in Ault Capital Group, but said it was too early to specify amounts. Cragun said pro forma financial information would be provided when the company files its S-4.
Ault said he plans to leave his executive role after the initial 20 megawatts are energized, with Horne taking over as chairman. Ault said he may remain a nonemployee board member, but would not make Hyperscale’s day-to-day decisions.
About Hyperscale Data (NYSEAMERICAN:GPUS)
Hyperscale Data, Inc., formerly known as Ault Alliance, Inc., is a diversified holding company focused on data center infrastructure and digital assets. Through its subsidiaries, the company develops and operates data centers intended to support high-performance computing and artificial intelligence workloads. The company also has activities in digital asset mining, including Bitcoin mining. Its data center operations are based in the United States, with facilities and planned expansion described by the company in Michigan.